Air conditioning for new build and self build homes: plan it early
Retrofitting air conditioning into a finished home is entirely possible, and we do it all the time. But if you are building a new home, extending heavily or doing a full renovation, you have a chance to make the installation almost invisible, with pipework and drains hidden in walls, floors and ceiling voids from the start.
This guide explains what to think about, at which stage of the build, so the air conditioning fits around your design rather than being squeezed in afterwards.
Planning a new system? See our air conditioning installation service.

Why timing matters so much
In a finished house, pipework has to run on the surface in trunking, through cupboards or along external walls, and indoor units go where those routes allow. During a build, the same pipes can be buried in stud walls, run between joists and dropped exactly where the indoor units are wanted.
Planning early also opens up options that are hard to add later, such as ducted systems hidden in a ceiling void, or a single outdoor unit in a discreet spot serving several rooms through a multi-split.
Stage 1: design
Ideally the installer sees the drawings while you can still make small changes. Useful questions at this stage include which rooms need cooling or heating, whether you want wall-mounted, ceiling cassette or ducted indoor units, and where the outdoor unit or units can go without annoying you or the neighbours.
Large glazed areas, rooflights and loft rooms all add heat in summer, so mention them. A sizing calculation based on the drawings gives each room the right capacity rather than a guess.
Stage 2: first fix
First-fix pipework is pressure tested and sealed so it stays clean while the rest of the build goes on. It is vital that other trades know where it runs, because a screw or nail through a hidden pipe is an expensive mistake to find later.
- Insulated refrigerant pipework run from each indoor unit position to the outdoor unit location
- Condensate drains laid to a fall, connected to a suitable waste point
- Power and communication cables between units
- A dedicated electrical supply allowed for in the electrician's plan
- Ceiling voids and access panels sized for any ducted or cassette units
Stage 3: second fix and commissioning
Once decorating is finished, the indoor and outdoor units are mounted and connected, the circuit is pressure tested again and evacuated, and the system is commissioned. Doing the second fix after decorating avoids plaster dust getting into new indoor units.
You then get a handover showing how the controls work and how to clean the filters, along with commissioning records for the system. Our guide to air conditioning commissioning explains what that stage should include.
Outdoor unit position
On a new build it is easy to forget the outdoor unit until the patio is laid and the planting is in. It needs solid ground or a bracket, free airflow, a short sensible pipe route and safe access for servicing. Keep it away from bedroom windows, yours and the neighbours', and check whether it needs planning consent where you are.
Ducted, cassette or wall-mounted?
Ducted systems hide the indoor unit in a ceiling void with only grilles visible, which suits new builds well because the void can be designed in. Ceiling cassettes suit larger open-plan spaces. Wall-mounted units are the simplest and easiest to service. Our comparison guides explain the trade-offs in detail.
Common new build mistakes
Each of these is easy to avoid at the planning stage and awkward to put right once the walls are closed up.
- Leaving the outdoor unit position until after landscaping is finished
- Forgetting to allow an electrical circuit in the electrician's design
- Running drains without enough fall, or with no accessible connection point
- Not protecting first-fix pipe ends, letting dust and moisture in
- Sizing systems before the glazing and insulation details are confirmed
Self builds and phased budgets
On a self build, budgets are often stretched by the time the house is weathertight. If the full system is not affordable straight away, it can still be worth installing first-fix pipework, drains and cables to the rooms you may want to cool later, and capping them off. Fitting indoor and outdoor units then becomes a simple second-fix job in a future year, without opening finished walls or ceilings.
Working with your builder
Agree early who is responsible for what: builders' work such as holes and making good, the electrical supply, and the drain connection. Share the pipe routes with every trade on site, and protect first-fix pipework ends until second fix. A short coordination conversation at the start saves a lot of rework.
Want a professional to handle it?
Related services
- Home air conditioning
- Air conditioning and refrigeration installations
- Air conditioning maintenance contracts
- Air conditioning breakdown repair
Covering Hertfordshire, Buckinghamshire, Bedfordshire and London.
FAQs
Common questions
When should I contact an air conditioning installer during a build?
At the design stage if possible, and certainly before first fix, so pipes and drains can be hidden in walls and ceilings.
Can air conditioning pipework be hidden in walls?
Yes, during a build or major renovation pipework and drains can run inside stud walls, floors and ceiling voids.
Is ducted air conditioning a good choice for a new build?
It often is, because the ceiling void can be designed to take it and only discreet grilles show in the rooms.
Do I need planning permission for an outdoor unit on a new house?
Some outdoor units can be installed under permitted development, but limits apply and rules vary. Check with your local planning authority.
When are the indoor units fitted?
Usually after decorating, at second fix, so plaster dust does not get into the new equipment.
Keep reading
More from our knowledge base
Cost & process guides
Air conditioning commissioning explained: the checks before handover
Commissioning is the set of tests and settings that prove a new system is sealed, correctly charged and working as designed before you start using it.
Cost & process guides
TM44 air conditioning inspections: what businesses need to know
Larger commercial air conditioning systems need a periodic energy inspection by an accredited assessor, separate from routine servicing and F-Gas leak checks.
Fault & symptom guides
Commercial fridge condenser cleaning: why it matters and how often
A dirty condenser is one of the most common reasons commercial fridges run warm, run constantly and break down, and it is one of the easiest to prevent.
Talk it through with an engineer.
No call centre — you speak to Ted directly.